Appendix A
Contract Number | Contractor | Contract Mod. No. | Controller Certification Date | Contract Expiration Date | Role | Key Deliverable(s), Contracted Date of Delivery, and Actual Date of Delivery | Contractor Selection Process | Airport Commission Approval (Resolution No. & Date) | Board of Supervisors Approval (Resolution & Date) | Total Certified Contract Budget $ | Closed/ Open/ Suspend | Notes |
4087.A | Airfield Development Engineering Consultant (ADEC) | Original | 18-Aug-99 | 01-Sep-01 | Geotechnical Engineering | Task A Final Report was due on 11-Feb-00 and delivered on 14-Feb-00. Of the 23 other reports required under this contract, nine have yet to be finalized. ADEC has been directed to minimize work activities. Therefore, finalization of the remaining reports is on an as-needed basis, as directed by ADB. | Competitive | 99-0226 / 13-Jul-99 | not required | 7,000,000 | Â | Â |
 |  | 1 | not required | not changed | (increase within original budgetary authority) |  |  | 99-0226 / 29-Oct-99 | not required | 0 |  |  |
 |  | 2 | not required | not changed | (expanded scope of work and internal contract adjustments) |  |  | 00-0058 / 22-Feb-00 | not required under previous legal opinion | 8,000,000 |  |  |
 |  | 3 | not required | not changed | (internal contract adjustments) |  |  | not required | not required | 0 |  |  |
 |  | 4 | 07-Nov-00 | 31-Dec-02 | (added geotechnical investigations) |  |  | 00-0222 / 2-Oct-00 | not required under previous legal opinion | 13,667,258 |  |  |
 |  | 5 | 02-Mar-01 | not changed | (finalized commercial terms of Mod 4) |  |  | Part 2 of 00-0222 / January 2001 | not required | 0 |  |  |
 |  | 6 | not required | 31-Dec-03 | (expiration date change only) |  |  | not required | not required | 0 |  |  |
 |  |  |  |  |  |  |  |  | Subtotals: | 28,667,258 | Suspended |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
4240.1 | URS Corporation (formerly URS Grenier Woodward Clyde) | Original | 07-Sep-99 | 31-Dec-01 | Preparation EIR/EIS (Phase I) | Draft EIR (summer of 2003) and draft EIS (winter of 2003). | Competitive | 99-0194 / 15-Jun-99 | not required | 1,100,000 | Â | Â |
 |  | 1a | 29-Mar-00 | not changed | (increase within original budgetary authority) |  |  | not required | not required | 0 |  |  |
 |  | 1b | 6-Jun-00 | not changed | (added environmental scope for Phase II) |  |  | 99-0451 / 21-Dec-99 | not required | 5,200,000 |  |  |
 |  | 2 | 01-May-01 | 31-Dec-02 | (added environmental analyses at request of regulatory agencies) |  |  | 00-0407 / 21-Nov-00 | not required under previous legal opinion | 5,000,000 |  |  |
 |  | 3 | 21-Aug-01 | not changed | (added environmental scope) |  |  | 01-0139 / 15-May-01 | not required under previous legal opinion | 500,000 |  |  |
 |  | 4 | 10-Oct-02 | 30-Jun-05 | (added environmental scope) |  |  | 02-0055 / 5-Mar-02 | 674-02 / 7-Oct-02 | 2,650,000 |  |  |
 |  | 5 | not certified | not changed | (FAA grant monies) |  |  | 02-0139 / 18-Jun-02 | 674-02 / 7-Oct-02 | 1,750,730 |  |  |
 |  | 5A | Pending | not changed | (release of reserved FAA grant monies) |  |  | 02-0055 / 5-Mar-02 | Pending | 3,540,828 |  |  |
 |  |  |  |  |  |  |  |  | Subtotals: | 19,741,558 | Suspended |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
5010.9 / 7000.9 | Luster/GKO | 5 | not certified | not changed | (to expand scope of services to include admin support services for the Runway Reconfiguration Project) | Â | Â | 99-0070 / 16-Mar-99 | not required under previous legal opinion | 750,000 | Â | A number of secondments were made under the Airport's existing Luster/GKO contract for the Airport Master Plan, but Luster/GKO itself was not contracted to provide direct services to ADB. |
 |  | 6 | 14-Dec-99 | not changed | (activities in support of the Runway Reconfiguration Project) |  |  | 99-0270 / 17-Aug-99 | not required under previous legal opinion | 700,000 |  |  |
 |  | 7 | 08-Mar-00 | not changed | (admin services for the Runway Reconfiguration Project) |  |  | 99-0427 / 7-Dec-99 | not required under previous legal opinion | 1,700,000 |  |  |
 |  | 8 | 08-Feb-01 | not changed | (staff assistance for Runway Reconfiguration Project) |  |  | 00-0428 / 5-Dec-00 | not required under previous legal opinion | 2,000,000 |  |  |
 |  |  |  |  |  |  |  |  | Subtotal: | 5,150,000 | Open |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
7000.1 | Erickson, Beasley, Hewiit & Wilson | Original | 29-Dec-99 | Until project completion | Legal services: eminent domain | Provision of as-needed legal services. | Competitive | 99-0173 / 1-Jun-99 | not required | 100,000 | Â | Â |
 |  |  |  |  |  |  |  |  | Subtotals: | 100,000 | Suspended |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
7000.2 | Howard, Rice, Nemerovski, Canady, Falk & Rabkin | 12 | 22-Nov-99 | Until project completion | Legal services: land use/environmental law - CEQA | Provision of as-needed legal services re land use and environmental issues pertaining to runway reconfiguration, and to act as the Airport's CEQA counsel. | Competitive | 99-0175 / 1-Jun-99 | not required | 100,000 | Â | This was Modification No. 12 to an existing contract, in order to broaden the contract's scope to cover ADB work. Total contract value now $1,345,000. |
 |  |  |  |  |  |  |  |  | Subtotals: | 100,000 | Suspended |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
7000.3 / 7000.16 | Hopkins & Sutter (7000.3) which later became Foley & Lardner (7000.16) | Original | 29-Dec-99 | Until project completion | Legal services: land use/environmental law - NEPA, air quality, environmental standards | Provision of as-needed legal services. | Competitive | 99-0173 / 1-Jun-99 [reassigned from Hopkins & Sutter to Foley & Lardner by Res. No. 01-0087 / 6-Mar-01] | not required | 100,000 | Â | Reassigned by the Airport Commission on 6-Mar-01 (Resolution 01-0087). |
 |  | 1 | 17-Dec-01 | not changed |  |  |  | 01-0148 / 15-May-01 | not required | 100,000 |  |  |
 |  |  |  |  |  |  |  |  | Subtotals: | 200,000 | Open |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
7000.4 | Remy, Thomas & Moose | Original | 26-Oct-99 | Until project completion | Legal services: land use/environmental law - wild life and water law, mitigation, permitting, CEQA | Provision of as-needed legal services. | Competitive | 99-0114 / 20-Apr-99 | not required | 50,000 | Â | Â |
 |  | 1 | 05-Jan-00 | not changed | (to continue services) |  |  | 99-0441 / 7-Dec-99 | not required | 100,000 |  |  |
 |  | 2 | 15-Jun-00 | not changed | (to continue services) |  |  | 00-0184 / 16-May-00 | not required | 200,000 |  |  |
 |  | 3 | 15-Dec-00 | not changed | (to continue services) |  |  | 00-0377 / 17-Oct-00 | not required | 300,000 |  |  |
 |  | 4 | 26-Jul-01 | not changed | (to continue services and hire subconsultants) |  |  | 01-0147 / 15-May-01 | not required | 300,000 |  |  |
 |  | 5 | 14-Oct-01 | not changed | (to continue services) |  |  | 01-0290 / 21-Aug-01 | not required | 500,000 |  |  |
 |  |  |  |  |  |  |  |  | Subtotals: | 1,450,000 | Open |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
7000.5 | Sheppard, Mullin, Richter & Hampton | Original | 29-Dec-99 | Until project completion | Legal services: environmental law - water quality, endangered species, U.S. Army COE, BCDC, State Lands | Provision of as-needed legal services. | Competitive | 99-0173 / 1-Jun-99 | not required | 100,000 | Â | Â |
 |  | 1 | 13-Mar-00 | not changed | (to continue services) |  |  | 00-0019 / 18-Jan-00 | not required | 200,000 |  |  |
 |  | 2 | 01-Mar-01 | not changed | (to continue services) |  |  | 00-0439 / 5-Dec-00 | not required | 200,000 |  |  |
 |  | 3 | 26-Jul-01 | not changed | (to continue services) |  |  | 01-0102 / 20-Mar-01 | not required | 250,000 |  |  |
 |  |  |  |  |  |  |  |  | Subtotals: | 750,000 | Suspended |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
7000.11 | DMC Airfield Engineers (DMJM Aviation, Mendoza and Associates, and Cabellon and Associates) | Original | 23-Apr-01 | 31-Dec-01 | Cost/Schedule Control Services and other Resources | Program management staff augment ADB staff. There are no specific deliverables to be completed by DMC staff. | Competitve | 01-0058 / 20-Feb-01 | not required | 5,350,000 | Â | Â |
 |  | 1 | 18-Dec-01 | 30-Jun-01 | (time only) |  |  | not required | not required | 0 |  |  |
 |  | 2 | 11-Aug-02 | 30-Jun-03 | (time only) |  |  | not required | not required | 0 |  |  |
 |  |  |  |  |  |  |  |  | Subtotals: | 5,350,000 | Suspended |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
7000.12 | Baker & McKenzie | Original | 09-Aug-00 | 09-Aug-02 | Environmental consulting services for Airfield Public Interest Group; permitting | Provision of on-call consulting services. | Competitive | 00-0199 / 6-Jun-00 | not required | 125,000 | Â | Â |
 |  | 1 | 02-Nov-01 | 31-Aug-02 | (reassigned contract to Steefel, Levitt & Weiss; added services; extended term) |  |  | 01-0127 / 18-Apr-01 | not required | 140,000 |  |  |
 |  |  |  |  |  |  |  |  | Subtotals: | 265,000 | Closed |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
7000.17 | O'Melvaney and Meyers | 3 | 15-Aug-01 | 15-Aug-04 | Legal services: environmental advice on the airfield reconfiguration program to NOAA. | Point of contact services between the Airport and NOAA, coordinating the NOAA Panel's work, and providing environmental advice on issues arising from NOAA Panel's work. | N/A | 01-0149 / 15-May-01 | not required | 50,000 | Â | Mod. No. 3 to an existing five-year contract for $150,000. |
 |  | 4 | 04-Jun-02 | not changed | (additional legal services) |  |  | 02-0049 / 19-Feb-02 | not required | 50,000 |  |  |
 |  |  |  |  |  |  |  |  | Subtotals: | 100,000 | Suspended |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
7012.1 | Environmental Science Associates | Original | 17-Aug-99 | 31-Dec-01 | Environmental review and permitting assistance | General services contract: tasks are ordered as required. | Competitive | 99-0195 / 15-Jun-99 | not required | 350,000 | Â | Â |
 |  | 1 | 04-Oct-00 | 31-Dec-01 | (to assist with Phase II of environmental planning) |  |  | 00-0248 / 6-Jul-00 | not required | 350,000 |  |  |
 |  | 2 | 17-Jul-01 | 31-Jul-02 | (to increase work effort and extend time) |  |  | 00-0412 / 21-Nov-00 | not required | 400,000 |  |  |
 |  | 3 | not required | not changed | (reduction in compensation) |  |  | not required | not required | (307,852) |  |  |
 |  |  |  |  |  |  |  |  | Subtotals: | 792,148 | Suspended |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
7013.1 | California Academy of Sciences | Original | 22-Mar-00 | 31-Dec-00 | Database of SF Bay flora and fauna species | Excel database / due 31-Dec-00 / delivered 30-Sep-02 | Sole source | 99-0115 / 20-Apr-99 | not required | 150,000 | Â | Â |
 |  | 1 | not required | 30-Sep-02 | (time extension) |  |  | not required | not required | 0 |  |  |
 |  | Credit |  |  |  |  |  |  |  | (4,953) |  |  |
 |  |  |  |  |  |  |  |  | Subtotals: | 145,047 | Closed |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
7013.2 | Bodega Marine Labs, UC Davis | Original | 01-Jun-00 | 01-Mar-01 | Study of herring and oyster habitats | Several documents, all delivered within negotiated extensions to their deadlines; last report currently suspended | Sole source | 99-0297 / 21-Sep-99 | not required | 306,000 | Â | Â |
 |  | 1a | not required | 31-Dec-01 | (time extension) |  |  | not required |  |  |  |  |
 |  | 1b | 05-Mar-02 | 31-Dec-02 | (added services and time extension) |  |  | 01-0268 / 7-Aug-01 | not required | 250,000 |  |  |
 |  | 2 | 31-Dec-03 | not changed | (time extension) |  |  | not required | not required | 0 |  |  |
 |  |  |  |  |  |  |  |  | Subtotals: | 556,000 | Open |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
7013.3 | Jones & Stokes | Original | 31-Jul-00 | 31-Oct-01 | Wetlands mitigation design | EIR on mitigation sites | Competitive | 00-0114 / 4-Apr-00 | not required | 800,000 | Â | Â |
 |  | 1 | 01-May-01 | 31-Dec-02 | (added services and time extension) |  |  | 00-0448 / 19-Dec-00 | not required | 3,350,000 |  |  |
 |  |  |  |  |  |  |  |  | Subtotals: | 4,150,000 | Suspended |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
7015.6 | Wildlands Inc. | Original | 21-Mar-02 | 31-Dec-06 | Option agreement for habitat mitigation credits (Skaggs Island) | Monthly payment to Haire Ranch | Sole source | 01-0358 / 4-Dec-01 | not required | 9,135,000 | Â | Â |
 |  |  |  |  |  |  |  |  | Subtotals: | 9,135,000 | Open |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
7021.1 | URS Corporation | Original | 18-Sep-98 | 31-Dec-98 | Runway reconfiguration study | Runway reconfiguration feasibility study delivered by March of 1999 (no due date specified by contract). Report analyzed 30 options and reported in detail on seven, including a "no-build" option. | Competitive | 98-0172 / 14-Jul-98 | not required | 1,356,000 | Â | Â |
 |  | 1 | 25-Feb-99 | 31-Dec-99 | (time extension) |  |  | not required | not required | 0 |  |  |
 |  | 2 | 15-Jul-99 | not changed | (additional airport planning services) |  |  | 99-0075 / 16-Mar-99 | not required | 350,000 |  |  |
 |  | 3 | 14-Dec-99 | 30-Jun-00 | (time extension) |  |  | not required | not required | 0 |  |  |
 |  | 4 | 20-Mar-00 | not changed |  |  |  | 00-0018 / 18-Jan-00 | not required | 200,000 |  |  |
 |  | 5 | not required | 31-Dec-00 | (time extension) |  |  | not required | not required | 0 |  |  |
 |  | 6 | 22-Jan-01 | 30-Jun-01 | (time extension) |  |  | not required | not required | 0 |  |  |
 |  | 7 | 28-Aug-01 | 30-Jun-02 | (time extension) |  |  | not required | not required | 0 |  |  |
 |  | 8 | 28-Feb-02 | 07-Mar-02 | (credit) |  |  | not required | not required | (49,201) |  |  |
 |  |  |  |  |  |  |  |  | Subtotals: | 1,856,799 | Closed |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
7021.2 | P & D Aviation | Original | 29-Dec-98 | 31-Dec-99 | Regional air transportation systems study | Planning report, due 4-Mar-99, delivered by 31-Dec-00. | Competitive | 15-Sep-98 / 98-0227 | not required | 500,000 | Â | Â |
 |  | 1 | 14-Jan-00 | not changed | (additional work) |  |  | 13-Jul-99 / 99-0238 | not required | 76,000 |  |  |
 |  | 2 | not required | 31-Dec-00 | (time extension) |  |  | not required | not required | 0 |  |  |
 |  | Credit |  |  |  |  |  |  |  | (24,580) |  |  |
 |  |  |  |  |  |  |  |  | Subtotals: | 551,420 | Closed |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
7021.3 | Howard, Needles, Tammen and Bergendorff (HNTB) | Original | 01-Dec-99 | 31-Oct-01 | Airspace/taxiway planning study | Final report due 28-Aug-00. Contract modifications added work to be incorporated into the final report, which was submitted in March of 2002. | Competitive | 99-0386 / 19-Oct-99 | not required | 1,824,466 | Â | Â |
 |  | 1 | 05-Nov-00 | not changed | (additional planning forecast of demand and facility requirements analysis) |  |  | already authorized under 99-0386 | not required | 125,534 |  |  |
 |  | 2 | 05-Jun-01 | not changed | (additional airspace capacity, aircraft capacity, delay, noise impact, and terps and part 77 analysis; supplemental layout plans) |  |  | 00-0157 / 2-May-00 | not required | 980,000 |  |  |
 |  | 3 | 29-Nov-00 | not changed | (additional airspace capacity and Oakland bridge/tunnel analysis) |  |  | 00-0294 / 15-Aug-00 | not required | 1,100,000 |  |  |
 |  | 4 | 07-May-01 | 30-Jun-02 | (define and simulate additional scenarios; time extension) |  |  | 01-0059 / 20-Feb-01 | not required | 1,930,000 |  |  |
 |  | 5 | 16-May-02 | 31-Dec-02 | (additional noise analysis; time extension) |  |  | 02-0044 / 19-Feb-02 | not required | 300,000 |  |  |
 |  | 6 | Certified but not dated | 31-Dec-03 | (additional analysis; time extension) |  |  | 02-0217 / 15-Oct-02 | not required | 300,000 |  |  |
 |  |  |  |  |  |  |  |  | Subtotals: | 6,560,000 | Suspended |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
7021.5 | Metropolitan Transportation Commission | Original | 11-Apr-00 | 30-Apr-00 | Regional Airport System Plan (RASP) Update | RASP update draft report, due 15-Apr-00, delivered 30-Jun-00. | Competitive | 99-0462 / 21-Dec-99 | not required | 213,500 | Â | Â |
 |  | 1 | 16-Mar-01 | N/A: SFO reimbursed MTC for its professional services subcontract and MTC managed the subcontract completion date. | (additional analysis required by BCDC) | Reimbursement of MTC professional services subcontract. |  | 00-0366 / 3-Oct-00 | not required | 100,000 |  |  |
 |  |  |  |  |  |  |  |  | Subtotals: | 313,500 | Closed |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
7022.1 | Federal Aviation Authority | Original | 25-Apr-01 | 25-Apr-04 | Air traffic control tower siting study | Provision of FAA staff assistance. | Sole source | 01-0085 / 6-Mar-01 | not required | 67,725 | Â | Â |
 |  |  |  |  |  |  |  |  | Subtotals: | 67,725 | Suspended |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
7031.1 | Solem & Associates | Original | 01-Nov-99 | 16-Aug-01 | Public affairs services | Communications strategies, materials, and messages; position papers; quarterly newsletter and website design; media training; media relations plan. | Competitive | 99-0196 / 15-Jun-99 | not required | 250,000 | Â | Â |
 |  | 1 | 06-Sep-00 | 01-Sep-01 | (increased funding) |  |  | 00-0250 / 6-Jul-00 | not required | 90,000 |  |  |
 |  |  |  |  |  |  |  |  | Subtotals: | 340,000 | Closed |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
7032.1 | Bay Relations | Original | 05-Oct-00 | 31-Jul-01 | Public information program focused on San Mateo County. | Strategic Public Information Outreach Plan and Schedule, due 04-Nov-00, delivered 03-Nov-00. | Competitive | 00-0138 / 18-Apr-00 | not required | 120,000 | Â | Â |
 |  | 1 | not required | not changed | (additional work; increased monthly retainer payment terms from $8,500 to $12,500) |  |  | not required | not required | 0 |  |  |
 |  | 2 | not required | 31-Jul-02 | (time extension) |  |  | not required | not required | 0 |  | Bay Relations' prime contract with the Airport Commission co-existed with Bay Relations' secundment under the DMC contract (05/01 - 07/02). A single project manager (Kandace Bender and her predecessor) was responsible for these simultaneous contractual arrangements for the same services, and ensured that Bay Relations only billed its monthly invoice against the DMC contract. Bay Relations' prime contract was kept open to institute Tom Kardos' plan to align all contracts on the same contract renewal date, but this plan was stymied by the post 09/11/01 budget reductions. Pending that decision, Bay Relations was seconded and paid under the DMC contract. |
 |  |  |  |  |  |  |  |  | Subtotals: | 120,000 | Closed |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
7033.1 | ER Group, LLC | Original | 14-Jul-00 | 23-Apr-01 | Public affairs program in Santa Clara County and the East Bay. | Situation analysis re current perceptions of key Santa Clara County decision makers, to be completed as directed by the Contract Manager, and delivered in October 2000. | Competitive | 99-0408 / 16-Nov-99 | not required | 100,000 | Â | Â |
 |  | 1 | 08-May-01 | 30-Apr-02 | (time extension) |  |  | not required | not required | 0 |  | ER Group's prime contract with the Airport Commission co-existed with ER Group's secundment under the DMC contract (05/01 -10/01). A single project manager (Kandace Bender and her predecessor) was responsible for these simultaneous contractual arrangements for the same services, and ensured that ER Group only billed its monthly invoice against the DMC contract. ER Group's prime contract was kept open to institute Tom Kardos' plan to align all contracts on the same contract renewal date, but this plan was stymied by the post 09/11/01 budget reductions. Pending that decision, ER Group was seconded and paid under the DMC contract. |
 |  |  |  |  |  |  |  |  | Subtotals: | 100,000 | Closed |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
7042.21 | T.Y. Lin International/ Ben C. Gerwick, Inc./ Han-Padron Assoc. | Original | 1-Apr-00 | 1-Aug-00 | Offshore runway construction concepts | A primary concept design due on 24-Jul-00 and delivered on that date. | Competitive | 00-0095 / 21-Mar-00 | not required | 250,000 | Â | Â |
 |  |  |  |  |  |  |  |  | Subtotals: | 250,000 | Closed |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
7042.22 | AGS, Inc. | Original | 04-May-00 | 15-Sep-00 | Offshore runway construction concepts | A primary concept design due on 24-Jul-00 and delivered on that date. | Competitive | 00-0096 / 21-Mar-00 | not required | 250,000 | Â | Â |
 |  |  |  |  |  |  |  |  | Subtotals: | 250,000 | Closed |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
7042.23 | Parsons Brinckerhoff, Quade & Douglas, Inc. | Original | 09-May-00 | 15-Sep-00 | Offshore runway construction concepts | A primary concept design due on 24-Jul-00 and delivered on that date. | Competitive | 00-0097 / 21-Mar-00 | not required | 250,000 | Â | Â |
 |  |  |  |  |  |  |  |  | Subtotals: | 250,000 | Closed |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
7042.24 | Peratrovich, Nottingham & Drage, Inc. | Original | 28-Jun-00 | 15-Sep-00 | Offshore runway construction concepts | A primary concept design due on 24-Jul-00 and delivered on that date. | Competitive | 00-0098 / 21-Mar-00 | not required | 250,000 | Â | Â |
 |  |  |  |  |  |  |  |  | Subtotals: | 250,000 | Closed | |
 |  |  |  |  |  |  |  |  |  |  |  |  |
7042.25 | The Dutra Group, Hydronamic bv, Bean Stuyvesant | Original | 24-Aug-00 | 15-Sep-00 | Offshore runway construction concepts | A primary concept design due on 24-Jul-00 and delivered on that date. | Competitive | 00-0099 / 21-Mar-00 | not required | 250,000 | Â | Â |
 |  |  |  |  |  |  |  |  | Subtotals: | 250,000 | Closed |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
7900.4 | Morrison & Foerster | 18 | 14-Oct-98 | Until project completion | Legal services: noise and environmental issues, FAA, air quality, administrative record | Ongoing legal services related to land use/environmental law. | N/A | 00-0456 / 19-Dec-00 | not required | 500,000 | Â | Extension of previous contract to add ADB-related work, for a total contract price of $7,000,000. |
 |  | Original | 08-Aug-01 | 08-Aug-04 | Aviation law services |  | Sole source | 01-0146 / 15-May-01 | not required | 500,000 |  | New contract signed on basis of firm's historic knowledge of Airport's environmental issues. |
 |  | 1 | 16-Dec-02 | not changed |  |  |  | 02-0222 / 15-Oct-02 | not required | 120,000 |  |  |
 |  |  |  |  |  |  |  |  | Subtotals: | 1,120,000 | Open |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
MEMORANDA OF UNDERSTANDING | Â | Â | Â | Â | Â | Â | Â | Â | Â | Â | Â | |
 |  |  |  |  |  |  |  |  |  |  | ||
7011.5 (MOU) | Bay Conservation and Development Commission | Original | 04-Sep-99 | 01-Jul-01 | Review of potential runway reconfiguration project (funds BCDC's contract with Donald Neuwirth & Associates) | (a) Donald Neuwirth's review of FAA and ADB documents; (b) BCDC's written comments on FAA documents | Sole source | Approved by Airport Director, 13-May-99 | not required | 200,000 | Â | Contract 7900.3 with Neuwirth & Associates became this MOU with BCDC. |
 |  | 1 | 04-Sep-01 | 30-Jun-03 | (additional staff and consultant reimbursement and MOU time extension due to extended project schedule) |  |  | 01-0012 / 9-Jan-01 | not required | 125,000 |  |  |
 |  | 2 | Pending | 30-Jun-04 | (time extension) |  |  | 02-0239 / 5-Nov-02 | not required | 125,000 |  |  |
 |  |  |  |  |  |  |  |  | Subtotals: | 450,000 | Open |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
7014.1 (MOU) | National Oceanic and Atmospheric Administration (NOAA) | Original | 07-Nov-01 | 30-Jun-02 | 19 member science peer review panel (second review panel onwards) | Written reports after each two-day meeting; not always timely. Final deliverable = written reports after Summer of 2003 meeting. | Sole source | 01-0121 / 18-Apr-01 | not required | 100,000 | Â | Â |
 |  | 1 | not required | 31-Dec-02 | (time extension) |  |  |  |  | 90,000 |  |  |
 |  | 2 | not required | 31-Dec-03 | (time extension) |  |  | 02-0229 / 5-Nov-02 |  | 0 |  |  |
 |  |  |  |  |  |  |  |  | Subtotals: | 190,000 | Open | First NOAA review panel met on October 19-20, 1999 under another contract. The NOAA review panel has met for two days in each of August 2001, May 2002, and December 2002 under this contract. |
 |  |  |  |  |  |  |  |  |  |  |  |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
 |  |  |  |  |  |  |  |  | TOTAL BUDGET: | 89,571,455 |  |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
PENDING | Â | Â | Â | Â | Â | Â | Â | Â | Â | Â | Â | |
7023.1 (Pending MOU) | State Lands Commission | Â | Pending | Pending | Ownership of submerged and reclaimed Bay land | Pending | Sole source | 02-0022 / 22-Jan-02 | Â | 50,000 | Pending | Â |
 |  |  |  |  |  |  |  |  |  |  |  |  |
(Pending MOU) | Regional Water Quality Control Board | Â | Pending | Pending | Review of potential runway reconfiguration project | Pending | Sole source | Pending | Â | 125,000 | Pending | Â |
 |  |  |  |  |  |  |  |  |  |  |  |  |
7066.1 (Pending MOU) | FAA | Â | Pending | Pending | Develop NAVAIDS technical data for the EIS/EIR | Pending | Sole source | 02-0021 / 22-Jan-02 | not required | 45,000 | Pending | Â |
 |  |  |  |  |  |  |  |  |  |  |  |  |
 |  |  |  |  |  |  |  |  |  |  |  | |
 |  |  |  |  |  |  |  |  |  |  |  |  |
 |  |  |  |  |  |  |  |  |  |  |  |  |
 |  | 4087 | Engineering studies (ADEK) |  |  |  |  |  |  |  | ||
 |  | 7000 | Program management (including legal services contracts) |  |  |  |  |  |  |  | ||
 |  | 7011 | Environmental studies (URS) |  |  |  |  |  |  |  | ||
 |  | 7012 | Permits (ESA) |  |  |  |  |  |  |  | ||
 |  | 7013 | Mitigation |  |  |  |  |  |  |  | ||
 |  | 7021 | Planning |  |  |  |  |  |  |  | ||
 |  | 7031 | Public affairs |  |  |  |  |  |  |  | ||
 |  | 7032 | San Mateo public affairs (Bay Relations) |  |  |  |  |  |  |  | ||
 |  | 7033 | Santa Clara public affairs (ER Group) |  |  |  |  |  |  |  | ||
 |  | 7041 | Peer review |  |  |  |  |  |  |  | ||
 |  | 7042 | Runway design/construction (offshore runway concepts) |  |  |  |  |  |  |  | ||
 |  | 7061 | Pavement & utilities design/construction |  |  |  |  |  |  |  | ||
 |  | 7071 | Land acquisition |  |  |  |  |  |  |  | ||
 |  | 7900 | Miscellaneous |  |  |  |  |  |  |  | ||
 |  |  |  |  |  |  |  |  |  |  |  |  |
 |  | ADB has also obtained services under existing Airport contracts with (1) John F. Brown Company for financial and economic analysis (ADB task ordered a benefit/cost analysis), (2) HMMH for noise abatement (ADB task ordered noise abatement measurement and analysis), and (3) The Allen Group/Cornerstone/EPC Consultants joint venture (for ADB contract management services). |  |  |  |  |  |  |  |